Air Force Base, Atlanta, GA - wastewater lift station - failed pump emergency turnaround History: * Friday, August 4, am - Pumping Machinery, LLC receives an emergency call - one of the existing two pumps failed * Friday, August 4, pm - our troubleshooting team completes examination of the site and initiates a station emergency rehab plan * Weekend of August 5/6 - work plan established and got ready * Monday, August 7 - failed pump is removed, examined, and retrofit drawings prepared * Week of August 7 - pumps emergency order placed, new supports fabricated, railing obtained, weld shop activated * Monday, August 14, am - new fabricated structure arrived, drain truck assisting to keep well dry, installation complete * Monday, August 14, pm - new pump installed, started, checked, and operational
Major spill problem avoided --------
OLD PUMPS REMOVED:
NEW PUMPS INSTALLED:
RETURN TO REPAIR and ENGINEERED UPGRADES CAPABILITIES PAGE . |