|
| |
Sizing Shims - How to?
Question:
How is the width and length
of a shim determined for leveling machinery during alignment or
installation? Are there general rule-of-thumb practices?
We have a recycle gas
Ingersoll-Rand barrel compressor powered by an Electric-Machinery 1500
hp/2300 Volt motor with a 3420-S frame. The motor rests on two continuous
60" long x 6" wide sole plates. The two motor feet measure 59" x 5" each.
What is the potential damage to alignment and/or the motor by using small
(6" x 6") shims versus large (24" x 6") or continuous (60" x 6") shims?
Jerry Choate
Murphy Oil USA, Inc.
Superior, WI 54880
Luis F. Rizo,
SABIC Innovative Plastics, offers
this advice:
Hello Jerry,
The
question you should focus on is... - How to create a monolith that will
absorb all of the force to the base and foundation of the equipment?
The unbalanced force of a reciprocating compressor is proportional to
the reactive force. In a liquid slug scenario as you probably know,
this force is not measurable, so it amounts to an "infinite" amount of
force. So I would try to get a shim as large as practical to cover the
width of the foot about the hold down bolt at each of the feet. Another
option is to a liquid chock to level and hold your machine down, so that
the complete structure becomes a monolith. I am attaching a few
pictures of a similar compressor grouted many years back, that it is
still operational today at the Exxon Baytown refinery/chemical plant
complex.
Below
are illustrations of an embedded optically set shim that has been
embedded using epoxy chock.

1.4 Leveling techniques for
horizontal baseplates
There are four
(4) methods to provide vertical adjustments to a horizontal baseplate.
A single wedge, parallel wedges, shim packs and jacking screws on metal
plates. The preferred method of the author is the jacking screw on
metal plates combined with metal shim plates. The following drawings
illustrate the 4 methods.


|

|

|
|
Leveling screw application |
Application of a wedge to assist in leveling |
|
No. |
Step
Description |
Date/initial |
|
1. |
Inspect all the shims to be sure that all are either 306 or 316
SS steel. |
|
|
2. |
Inspect the shims to be used to make sure that no single shim
less than 0.005 in.(.13mm)is used by itself. Any smaller shims
must be sandwiched between heavier shims (0.040in. (1mm) to
0.060 in. (1.5mm)). |
|
|
3. |
Verify that large stacks of shims have been replaced with
equivalent thicker shims to avoid creating a spring condition
under the base as a support. |
|
|
4. |
Verify that the initial stack of shims under the baseplate is
sufficiently large to allow for multiple level adjustments. For
example start with a shim pack under each foot made up of one
0.062 in.(1.6mm) and one 0.31in. (7.9mm), one 0.025in. (1mm) and
two 0.015in. (.5mm), 0.010in. (.25mm) and .005in.(.127mm) (This
combination has proven to allow great adjustment flexibility.) |
|
|
5. |
Check, with a torque wrench, that all anchor bolts have been
properly tightened to the same torque value. Check to make sure
that this procedure is followed after every shim change. See
standard torque values for B-7 bolts for the diameter used. |
|
|
6. |
Using a machinist level (Starrett 98 or a master level) check
the level of the pads with respect to each other. Maximum out
of level is 0.002 in.(0.05mm) |
|
|
7. |
Inspect that all the machined surfaces on the baseplate are
leveled within 0.0005 in. (0.013mm) / foot in two directions 90o,
after the anchor bolts have been snugged down. Use of a master
level (0.0005 in./div.) is recommended. Do not exceed an
overall level variation greater than 0.010 in. (0.25mm). |
|
|
8. |
Inspect that the shim packs or wedges used for leveling are
located on both sides of the foundation bolt. |
|
|
9. |
Inspect that the baseplate height has been set to the correct
elevation as call for in the drawing. |
|
|
10. |
Check that all the leveling devices are in full and solid
contact with the concrete or the baseplate. |
|
|
11. |
After final anchor bolt tightening, recheck level. Do not
exceed 0.010 in./ (0.25mm) maximum out of level over the entire
length of the baseplate. Consult the responsible reliability
team member before continuing. |
|
|
12. |
When all the above steps have been accepted, the baseplate
leveling is complete and the baseplate is ready to be grouted. |
|
Copyright Ó
Elfer, Inc. 1999 Rev. 1, Waterford, New York
 
Luis F. Rizo, PE
SABIC Innovative Plastics
IT Sourcing Services Manager
Julien Le Bleu also adds:
First question is generally try to size the
shims to match the feet if possible. When I was with GE we often had
large sole plates. Would make several non-shrink grout pads along
the length of the plate and the same width as the plate. This was
done after the plate was leveled with jacking screws and checked for
not humping or sagging. The small pads were made with Styrofoam and
liquid non shrink grout poured in and allowed to set up.
The plate was then pulled and the foam form was removed. The grout
was cleaned and the plate set down again. If all is correct make
another form around the entire plate and pour non-shrink grout into
it and have it include the small pads poured previously.
If the plates need to be shimmed up to get to elevation do it with
stainless steel shims on each of the small pads. When all is as you
need it then do the step above and put it all in the final pour of
non-shrink grout.
Julien Le Bleu
Back to PUMP MAGAZINE Page
|