History:

* Friday, August 4, am - Pumping Machinery, LLC receives an emergency call - one of the existing two pumps failed

* Friday, August 4, pm - our troubleshooting team completes examination of the site and initiates a station emergency rehab plan

* Weekend of August 5/6 - work plan established and got ready

* Monday, August 7 - failed pump is removed, examined, and retrofit drawings prepared

* Week of August 7 - pumps emergency order placed, new supports fabricated, railing obtained, weld shop activated

* Monday, August 14, am - new fabricated structure arrived, drain truck assisting to keep well dry, installation complete

* Monday, August 14, pm - new pump installed, started, checked, and operational

 

Major spill problem avoided --------

 

OLD PUMPS REMOVED:

 

 

NEW PUMPS INSTALLED:

 

BEFORE

AFTER

 RETURN TO REPAIR and ENGINEERED UPGRADES CAPABILITIES PAGE

 .